Kitchen Remodeling Planning Guide

White shaker upper cabinets to the ceiling with navy shaker lower cabinets and a farmhouse sink

A step-by-step guide to planning a kitchen remodel in South Florida, from goals and budget to HOA approvals, permits, hurricane season and living through the work.

A kitchen remodel touches nearly every trade in the house: cabinetry, countertops, plumbing, electrical, flooring and often walls. Good planning is what keeps it on schedule and on budget. This kitchen remodeling planning guide walks through the process in the order decisions actually need to be made, with notes on the factors that are specific to South Florida, including condo and HOA approvals, local permitting and hurricane season.

Step 1: Define Your Goals

Start with why you are remodeling. The answer shapes every decision that follows.

  • Function: more storage, better workflow, room for two cooks, a bigger island.
  • Style: updating a dated look or making the kitchen match the rest of the home.
  • Condition: replacing worn, damaged or water-affected cabinets.
  • Resale: preparing a home for sale or rental.

Write down your top three priorities and your biggest frustrations with the current kitchen. Collect photos of kitchens you like and note what specifically appeals to you, whether it is a color, a layout or a storage idea. Our modern kitchen design ideas post is a good place to start.

Step 2: Decide on the Scope

Remodels generally fall into three levels:

  1. Refresh: new countertops, hardware, backsplash or lighting, keeping existing cabinets.
  2. Cabinet and countertop replacement: new cabinetry and surfaces in roughly the same layout.
  3. Full remodel: a new layout, which may involve moving plumbing, gas or electrical, removing walls, and new flooring.

Keeping the existing layout usually saves time and money, because plumbing and gas lines stay in place. Moving the sink or range, or removing a wall, expands the project and typically brings in permits and more trades.

Step 3: Set a Realistic Budget

Build your budget around the scope, and include everything:

  • Cabinetry, hardware and organizers
  • Countertops and backsplash
  • Appliances, sink and faucet
  • Plumbing, electrical and lighting
  • Flooring, drywall and paint
  • Demolition and disposal
  • Permit fees and any association requirements
  • A contingency for surprises behind walls and under floors

Older homes in particular can reveal issues once cabinets come out, such as old water damage or outdated wiring, so a contingency is important. For a closer look at what drives cabinet pricing, see how much custom kitchen cabinets cost.

Step 4: Design and Measure

Design is where you avoid expensive mistakes. A good design phase includes:

  • Accurate field measurements, including ceiling height, windows, doors and utility locations.
  • A layout with clear work zones and comfortable walkways.
  • Appliance specifications, since cabinet openings must match exact models.
  • Storage planned around what you own.
  • Material, finish and countertop selections reviewed together.

Seeing the design in 3D before production makes it much easier to judge proportions and colors. At Royce Kitchen & Closet, the consultation is free and we create a 3D model for you to review before providing an estimate. More about that on our cabinet design page.

Step 5: Condo and HOA Approvals

In South Florida, many homeowners live in condominiums or communities with homeowners' associations, and those associations often have their own requirements for renovations. Check your documents and talk to management early, because approvals can take time. Common requirements include:

  • A written renovation application with a description of the work and sometimes drawings.
  • Proof of contractor licensing and insurance, sometimes naming the association.
  • Restricted work hours and days.
  • Elevator reservations and protection for deliveries and debris removal.
  • Rules about flooring underlayment for sound control in multi-story buildings.
  • Restrictions on moving plumbing or altering walls.
  • A deposit against damage to common areas.

Requirements vary from building to building. We'll walk you through what your building or HOA may require, but the association has the final word, so get its rules in writing before you finalize a schedule.

Step 6: Permits

Whether you need a building permit depends on the scope of work and on your local building department. Cabinet and countertop replacement in the same layout is treated differently from work that alters plumbing, electrical, gas lines or walls. In South Florida, permits are issued by the city or county where the home is located, and requirements differ between jurisdictions.

The safe approach is to check requirements with your local building department before work begins. Skipping a required permit can cause problems with insurance claims, inspections and future home sales. Your contractors for plumbing and electrical work should be able to explain what applies to their portion of the job.

Step 7: Plan Around Hurricane Season

Atlantic hurricane season runs from June 1 through November 30. Remodels happen year-round in South Florida, but it is wise to plan for the season:

  • Build in schedule flexibility. A storm threat can pause work for a few days while crews secure job sites and homeowners prepare.
  • Think about a working kitchen. If a storm arrives mid-project, you may want basic food-prep and water access. Plan a temporary setup.
  • Protect materials. Cabinets and slabs delivered to the home should be stored indoors, off the floor, and away from openings.
  • Consider timing. Some homeowners, especially seasonal residents, prefer to schedule work for the cooler, drier months. Others take advantage of quieter summers. Either can work with planning.

Step 8: Understand Lead Times

Several items in a kitchen remodel are ordered or built well before installation day:

  • Custom cabinetry is built to order after the design is approved.
  • Countertops are typically templated after cabinets are installed, then fabricated, so they follow the cabinets.
  • Appliances can have variable availability, and cabinet openings depend on exact models, so choose and order them early.
  • Special-order fixtures and tile may also take time.

Ask each supplier for a realistic timeline and build your schedule backward from the date you want to be cooking again. Avoid making changes after production starts; that is the most common cause of delays.

Step 9: Prepare for the Work

  • Empty the cabinets and pantry completely; it is a good time to declutter.
  • Clear a path from the entry to the kitchen for deliveries and debris removal.
  • Protect nearby floors and furniture, and plan for dust control.
  • Make arrangements for pets and children during noisy or messy phases.
  • Confirm parking, building access and work hours with your association if applicable.

Step 10: Living Through the Remodel

The weeks without a full kitchen are easier with a plan.

Set up a temporary kitchen

  • Use a spare room, dining area or garage with a refrigerator, microwave, toaster oven or countertop induction burner, and a coffee maker.
  • Keep a small set of dishes and utensils; wash them in a bathroom or laundry sink.
  • Plan simple meals and stock up on easy options before demolition.

Keep communication clear

  • Know who to contact for each part of the job.
  • Walk the site regularly and ask questions early.
  • Keep a running list of items to review before final sign-off.
Farmhouse sink set into navy shaker cabinets with white quartz countertops
Details like sink placement and cabinet finish are settled during design, long before installation.

Protect your home and your health

  • Ask that dust barriers be put up between the work area and the rest of the home.
  • Change or cover HVAC return vents near the kitchen so dust does not circulate through the system.
  • Keep a fire extinguisher accessible in your temporary kitchen.

A Typical Order of Work

  1. Design, selections and approvals
  2. Ordering and production
  3. Demolition
  4. Rough plumbing and electrical, with inspections if required
  5. Drywall and flooring as needed
  6. Cabinet installation
  7. Countertop templating, fabrication and installation
  8. Backsplash, fixtures, appliances and lighting
  9. Final adjustments and walk-through

Every project differs, but understanding this sequence helps you see why decisions have to be made in order.

Ready to Start?

Royce Kitchen & Closet works with homeowners from design through cabinet installation and complete renovations. Read more about our kitchen remodeling services and cabinet installation, or call (954) 928-8146 to talk through your plans.

Questions & answers

Frequently Asked Questions

Do I need a permit to replace kitchen cabinets in South Florida?

It depends on the scope of work and your local building department. Work that alters plumbing, electrical, gas or walls is more likely to require a permit. Check requirements with your city or county building department before starting.

Do condo associations need to approve a kitchen remodel?

Many do. Associations often require a renovation application, contractor insurance documentation, set work hours and elevator reservations. Review your building rules and contact management early.

Is it a bad idea to remodel during hurricane season?

Not necessarily. Remodels happen year-round in South Florida. Build some flexibility into the schedule, store materials safely indoors and plan a basic temporary kitchen in case a storm interrupts work.

What should I decide first in a kitchen remodel?

Start with your goals and scope, then your budget, then layout and appliance selections. Cabinet openings depend on exact appliance models, so appliances should be chosen before the cabinet design is finalized.

How do I cook during a kitchen remodel?

Set up a temporary kitchen in another room with a refrigerator, microwave or countertop cooking appliance and a coffee maker. Plan simple meals and keep a small set of dishes for washing in another sink.